Feed water pump installation, CHP Plant Jindřichův Hradec, Czechia

Feed water pump installation, CHP Plant Jindřichův Hradec, Czechia
Owner's Engineer Design and Studies Installation and Supply Diagnostics

We coordinated the design process and assisted during installation and commissioning of feed water pump in biomass CHP plant. We provided the design and strength recalculation of the new high pressure pipelines.

BFS Industry activities:

  • Design and strength recalculation of pipelines
  • Coordination of installation works
  • Coordination of commissioning

“Brownfield” project

Execution date: 12/2017 - 01/2018

Technical specifications of the pump:

  • Pump head: 8 MPa
  • Mass flow: 40 t/h