HEAT STORAGE SYSTEM, RIGA CHP-2 PLANT, LATVIA

HEAT STORAGE SYSTEM, RIGA CHP-2 PLANT, LATVIA
Owner's Engineer Design and Studies Installation and Supply Diagnostics

Following the successful development of preliminary design, we have also prepared the technical specification for procurement of the turn-key supplier of the whole heat storage system. The heat storage system will be integrated into Riga CHP-2 plant in Latvia. The CHP plant consists of two CCGT units and five hot-water boilers and supplies heat into the district heating system of Riga.

BFS Industry activities:

  • Adaptation of the preliminary design for the procurement purposes
  • Development of the technical specification
  • Development of the methodology for guaranteed parameters demonstration
  • Pre-tender communication with potential tenderers

Location: Riga, Latvia

Execution dates: 05/2018 - 07/2018

Technical specifications of the storage system:

  • Water volume: 17,800 m3
  • Charging/discharging power: 150 MWt
  • Capacity: 550/1000 MWh
  • Atmospheric type
  • Temperature difference 95/67 °C
  • CHP plant total electric power output: 832 MWe
  • CHP plant total heat output: 1124 MWt