Implementation of equipment for the provision of transmission system ancillary services to the Energo Příbram Heating Plant, Czechia

Implementation of equipment for the provision of transmission system ancillary services to the Energo Příbram Heating Plant, Czechia
Owner's Engineer Design and Studies Installation and Supply Diagnostics

We prepared a study addressing the technical and legislative aspects of the installation of a 12 MW airboiler system for installation at the Energo Příbram premises for the provision of transmission system ancillary services. It was also about the formulation of CAPEX and OPEX, a simplified comparison with the hot water electric boiler's option and recommendations for further steps in the project, including an economic evaluation of the return of individual options.

BFS Industry activities:

  • Demand procedure for necessary technologies and constructions
  • Development of the study
  • Consultation with the building authority

Location: Příbram, Czechia

Study development: 06/2022 - 07/2022

Technical specifications:

  • Electrical input of the technology: 12 MW
  • Electric boiler voltage: 10.5 kV"