Steam, 30 MW, high voltage electric boiler, Pilsen, Czechia

Steam, 30 MW, high voltage electric boiler, Pilsen, Czechia
Owner's Engineer Design and Studies Installation and Supply Diagnostics

Our Company:

  • prepared the project documentation for the mechanical (piping) part,
  • in the role of Chief Project Engineer, coordinated the designers of the LV electrical, HV electrical, civil, and mechanical parts,
  • took on the role of project manager for the mechanical, LV electrical, and civil parts,
  • provided engineering services for construction (permitting),
  • performed commissioning of the technology,
  • programmed the automated control of the technology in a Simatic PLC,
  • coordinated the certification of the technology for the provision of ancillary services.

Technical parameters:

  • Electrical input of the electric boiler: 30 MW
  • Electric boiler voltage: 10.5 kV
  • Electrical input of the electric steam superheater: 1.9 MW
  • Superheater voltage: 0.4 kV
  • Steam overpressure: 1.18 MPa
  • Superheated steam temperature: 260°C
  • Certified ancillary services: aFRR, mFRR

Location: Pilsen, Czech Republic
01/2024 – 12/2025