Construction of a backup heating plant at the Hodonin Power Plant – Electric boiler plant

Construction of a backup heating plant at the Hodonin Power Plant – Electric boiler plant
Owner's Engineer Design and Studies Installation and Supply Diagnostics

Our company prepared the documentation for the building permit for the new steam electric boiler project at the Hodonín Power Plant, which will serve as a backup steam source and as an active element in providing ancillary services to the Czech Republic’s transmission system.

Technical parameters of the project:

  • Electric input of the electric boiler: 20 MW
  • Nominal steam output: 33 t/h

Role of BFS Industry in the project:

  • Preparation of the documentation for the building permit