Hazardous waste incineration plant, Kolín, Czechia

Hazardous waste incineration plant, Kolín, Czechia
Owner's Engineer Design and Studies Installation and Supply Diagnostics

We assessed the existing technology condition and developed a feasibility study on the general overhaul of the incineration plant. Study was supported by findings from negotiations with potential technology suppliers.

BFS Industry activities:

  • Assessment of the existing technology condition
  • Elaboration of feasibility study
  • Negotiation with potential technology suppliers

Execution date: 09/2017 - 11/2017

Technical specifications of the incineration plant:

  • Waste: dangerous waste
  • Annual plant capacity: 3 500 tons of waste